Re: Inaccurate and unreliable behaviour from tasks.
Aldevinas Katkus
4-24-17
Have you checked the Project Transactions register? This is the place where billable activities are stored.
We haven't noticed anything like you, even though we use activities every day.
More explanation @Paul:
When the issue occurs, should see if restarting presence or lookup helps. If so - that is the issue and should be sorted. First need to ensure that that is the issue...
Hello!
You can mark it as closed as option. If document is connected with other documents you can not delete it so you will not be able to delete PO, as you will not be able to remove Goods receipt...